Felicia Children's Center Development Timeline

2025
August 2025 – Investment: $1352
August 2025 – Investment: $1352
  • Jeny (our unpaid intern) has been promoted to Assistant Operations Manager and is now salaried
  • health insurance purchased for all staff
  • fees paid for Ruth to attend a 2-week Montessori conference in the capital city of Dodoma in September
  • perimeter wall engineer onsite to plan wall construction and necessary gates
July 2025 – Investment: $6000
July 2025 – Investment: $6000

Immersion week at FCCF!!

 

Felicia, her husband Jeff, daughter/and teacher Allie, and family friend Seth spent a week volunteering, teaching, playing, and getting to know the children and staff.

 

An exceptional team of 6 medical and dental professionals from Health Mission Africa visited our school.  Each child had a complete exam, and all were screened for typhoid, malaria, hepatitis, and HIV (all tested negative for all!)

 

  • The dental team came another day to give a presentation on oral hygiene education/tooth brushing
  • First Aid box/supplies purchased, as well as needed medications for some of the children for common/treatable illnesses
  • All children given deworming meds- this will continue every 3 months/ cost covered by the Tanzanian government
  • Additional $ allocated for food to add a nutritious protein “peanut butter” ball snack to the school meal plan as suggested by the doctors to continue to improve the health of our children
  • Printer and paper purchased for operations staff
  • General cleaning/kitchen supplies purchased, such as buckets, mops, rubber gloves, garbage bags, and plastic bins to organize classroom materials and to make “cubbies” for the children’s personal items and schoolwork to bring home
  • 10 classroom bookcases built onsite by Jeff, Seth, Frank and Joel Laizer (Ruth’s son’s)
  • Extra food purchase for a Fourth of July celebration for students, staff, the Laizer family, and all of us!
  • All supplies that were hand-carried by us were organized in the classrooms on the bookcases
  • Charts and classroom charts were hung in both classrooms and utilized by the teachers, including Allie
June 2025 – Investment: $3975
June 2025 – Investment: $3975
  • necessary shift of Tanzania books to our U.S. accounting firm LIFMS for utmost transparency/accuracy
  • purchased wood, paint, and materials for classroom bookcases
  • purchased Nike sneakers for all students for outdoor play
  • set up a new dedicated FCCF bank account at Stanbic Bank with online access/better banking features
  • website enhancements
May 2025 – Investment: $7655
May 2025 – Investment: $7655
  • completion of the “Barr playground”
  • grass planted in playground area
  • completion of uniforms for all enrolled children
  • onsite dental and medical checkups scheduled for early July
Apr 2025 – Investment: $4213
Apr 2025 – Investment: $4213
  • $20k invested into a low risk brokerage account in the US
  • deposits made for the playground and permits needed
  • website enhancements
  • deposit made for sample uniforms
  • Easter celebration
  • all staff are now salaried employees
Mar 2025 – Investment: $5686
FCCF cocktail party announcement
  • website now live!
  • Susan Kim was elected to the Board of Directors
  • fundraiser held in NYC on March 10th
  • permits purchased for our playground
  • deposits made for playground
  • uniform samples requested
Feb 2025 – Investment: $7110
picture of seesaw for playground equipment
  • website design fees
  • mats for nap time received from the US
  • cleaning supplies purchased
  • fundraiser planned, invites sent, deposit for venue, visuals created for presentation
  • computer purchased for Lotha
  • accounting firm LIFMS hired in the US
  • playground designed
  • paid engineer fees to cost out the kitchen/dining building
Jan 2025 – Investment: $3200
Jan 2025 – Investment: $3200
  • website development
  • we held our first Board Meeting January14th
  • hired a local architect in TZ to design a kitchen/dining building
  • purchased school supplies
  • purchased/installed curtains in classrooms
  • purchased desks and chairs for the teachers
  • purchased more bricks for the perimeter wall
2024
Dec 2024 – Investment: $2465
picture of inside of classroom
  • IRS #1023 filed- projected 6-8mo before official approval as 501c3
  • Mats shipped for resting from School Supply
  • Cooking utensils purchased
  • Water filtration system purchased
  • Christmas celebration- crafts, take-home food prepared for families

 

Nov 2024 – Investment: $635
bricks for exterior wall
  • Paul hired as our accountant
  • Computer purchased/quick books subscription
  • Bricks for wall purchased- just a start to gather materials as we can fund
  • Susan hired to formalize logo, brand development, website and social media and assist with event management